Córdoba City Council adapts 13 schools to the heat for 1.54 million, around 118,000 euros per school

(Madrid time)

Over these seven days in the Córdoba comarca, the City Council has handed out the climate adaptation of 13 schools, bidding on two homes ends this Monday among five auctions, 16 new companies are registered and the Junta, Andalusia's regional government, puts 20.77 million towards energy in housing and firms.

Works at thirteen schools run by Córdoba City Council are now awarded, and four street and square projects await a contractor

Córdoba, 28 September 2026. The schools contract outweighs the other four put together
Amount before VAT of each municipal works contract, in euros. Córdoba, 28 September 2026. Source: Public Sector Procurement Platform · CASAS.ES · CC BY 4.0

Four flats and a shop unit within Córdoba city limits go to court auction, two of them closing this Monday 28

Córdoba, 28 September 2026. Three of the five auctions end this week
Auctions in the city of Córdoba by the week bidding ends. Córdoba, 28 September 2026. Source: BOE Auction Portal · CASAS.ES · CC BY 4.0

Sixteen firms register across the Córdoba comarca in seven days, with 128,160 euros between them, but only one residential builder

Córdoba, 28 September 2026. Three in four companies start with 3,000 euros
Share of the week's 16 incorporations that falls below each level of capital. Córdoba, 28 September 2026. Source: BORME · CASAS.ES · CC BY 4.0

The Cerro Muriano hostel, at 988,457 euros, leads the works awaiting award across the municipality of Córdoba

Córdoba, 28 September 2026. From announcement to works
Four works contracts in the city of Córdoba by the stage they have reached. Córdoba, 28 September 2026. Source: Public Sector Procurement Platform · CASAS.ES · CC BY 4.0

Andalusia's Junta shares out 20.77 million across three energy lines for homes and businesses, with applications from 22 October

Córdoba, 28 September 2026. Seven in ten euros go to households and communities
Budget of the three Junta energy lines that reach the Córdoba comarca, in euros. Córdoba, 28 September 2026. Source: BDNS · CASAS.ES · CC BY 4.0

See the CasasValue of any building in the Córdoba comarca on the map

From 20 to 27 September, the city of Córdoba, the only municipality in its comarca, saw the City Council award the climate adaptation of 13 schools, four street and square works and the Cerro Muriano hostel were still being assessed, bidding opened on a commercial premises, 16 companies were registered and the regional Junta called 20.77 million in energy grants.

Every figure links to its official document. If something does not add up, reply and we will correct it within 24 hours. Córdoba Análisis y Negocios Semanal is published by CASAS.ES.

📰 Journalist or publisher? You can republish this analysis and its charts for free under CC BY 4.0, as long as you credit CASAS.ES and link to this page.

Source: CASAS.ES, Córdoba Análisis y Negocios Semanal, 28 September 2026. https://casas.es/en/analysis/cordoba/2026-09-28/city-council-adapts-13-schools-heat-around-118000-euros/

RSS