Analysis🏠 My home

Analysis / Comarcas / Valle del Guadalhorce comarca / 19 October 2026

VALLE DEL GUADALHORCE ANÁLISIS Y NEGOCIOS SEMANAL

Valle del Guadalhorce comarca · No. 4 · Monday 19 October 2026 · 5-minute read

Casarabonela settles on the firm for a 1.07 million covered municipal sports centre

(Madrid time)

In Málaga's Valle del Guadalhorce comarca, Casarabonela assigns its 1.07 million sports centre plus the Qasr Bunayra castle works, five open tenders total 1.7 million and eleven firms are founded, four in Coín.

One sports centre makes up 93.5 of every 100 euros Casarabonela has handed to a firm

Valle del Guadalhorce, 19 October 2026. Casarabonela makes up 8.1 per cent of the works with a company
Tender value before VAT of the nine works in the comarca that have a company. Area proportional to euros. Valle del Guadalhorce, 19 October 2026. Source: Public Sector Procurement Platform · CASAS.ES · CC BY 4.0
  • The covered hall is now assigned to builders. Casarabonela lists on the Plataforma de Contratación, the official portal where public bodies publish their tenders for works and services, where the covered municipal sports hall is at award stage, when the public body picks the firm, going to UTE PABELLÓN CASARABONELA, a UTE, a temporary joint venture of firms bidding together. Tendered at 1,074,378.69 euros before VAT.
  • The Qasr Bunayra castle also has a builder. The same council lists as closed, the tender being over and the contract signed, the restoration of the archaeological remains of the Qasr Bunayra Castle-Fortress, with Construcciones Bonela S.L. It went to public tender, where firms bid to do works or a service, at 74,267.38 euros before VAT.

Five tenders offer 1.7 million from Cártama to Pizarra

Valle del Guadalhorce, 19 October 2026. Two close on Thursday 22, the other three run until 5 November
Works in the Valle del Guadalhorce comarca open for bids, at 10, 20 and 30 km from Coín. Valle del Guadalhorce, 19 October 2026. Source: Public Sector Procurement Platform · CASAS.ES · CC BY 4.0
  • Guaro, Yunquera and Pizarra published three tenders in four days. Between 13 and 16 October came Guaro's sanitation and sewerage for calle Barranco, tendered at 71,646.21 euros before VAT with bids until 28 October, Yunquera's upgrade of calle Calvario, tendered at 92,561.98 euros before VAT and open until 4 November, and Pizarra's completion of the development of calle Higuera, tendered at 117,812.44 euros before VAT, with bids until 5 November.
  • Asphalt and paving run down to Thursday 22. Still open are the repair of paving in Cártama municipality, tendered at 1,194,134.28 euros before VAT, and the Alhaurín de la Torre 2026 asphalt plan, tendered at 227,271.52 euros before VAT.

Seven works tendered at 13.0 million already sit with contractors across Alhaurín de la Torre, Coín and Cártama

Valle del Guadalhorce, 19 October 2026. The car park weighs almost as much as the other six combined
Tender value before VAT of the seven works with a company in Alhaurín de la Torre, Coín and Cártama, log scale. Valle del Guadalhorce, 19 October 2026. Source: Public Sector Procurement Platform · CASAS.ES · CC BY 4.0

Santo Cristo, Cañadilla Víquez and two Alhaurín el Grande projects, 1.1 million past the bidding stage

Valle del Guadalhorce, 19 October 2026. Where these four works stand
Stages of the file on the Procurement Platform for the four tenders in this section. Valle del Guadalhorce, 19 October 2026. Source: Public Sector Procurement Platform · CASAS.ES · CC BY 4.0

Eleven new companies put in 154,610 euros in the comarca, and Coín contributes four

Valle del Guadalhorce, 19 October 2026. Two companies hold more than four in every five euros
Cumulative share of the 154,610 euros of capital of the 11 companies in the BORME from 14 to 16 October. Valle del Guadalhorce, 19 October 2026. Source: BORME · CASAS.ES · CC BY 4.0
  • Eleven companies are founded between 14 and 16 October. The BORME, the Official Gazette of the Companies Register, where new firms must by law be published, lists in its issues of 14, 15 and 16 October 11 incorporations in the comarca, with 154,610 euros of share capital, the money partners put in at the start.
  • A metalwork firm in Coín starts with 77,500 euros. It will make metal doors and windows and build homes (BORME of the 16th). With it, four building start-ups add up to 86,510 euros: a residential builder in Alhaurín el Grande, a workshop in Coín that adds property development and BUDDIES MAINTENANCE SL, a bricklaying firm, also in Coín.
  • HORMICADO puts 50,000 euros into transport in Pizarra. Rounding out the list are SISTEMAS Y PROCESOS INTELIGENTES SL (BORME of the 14th) and FUNCTIONAL BROTHERS SL (BORME of the 16th) in Alhaurín el Grande, ALHAURIN 360 SL in Alhaurín de la Torre (BORME of the 15th), GRUPO COMIENZOS INNOVA SL in Coín, a hospitality firm in Alhaurín el Grande and a holding company in Cártama, a firm whose business is owning stakes in other firms.
  • Four new Andalusian calls, from 2027 milk recording to work-life balance. The BDNS, the National Grants Database, where every administration posts its grants, lists the call, the notice opening applications, for 2027 dairy yield recording and three Andalusian work-life balance lines, general, farming and fishing.

Check on the CASAS.ES map the CasasValue of any building in Alhaurín de la Torre, from Isaac Peral to Pinos de Alhaurín

Casarabonela heads the autumn building season in Málaga's Valle del Guadalhorce comarca, as both a covered municipal hall and works at Qasr Bunayra fortress gain a builder. Guaro, Yunquera and Pizarra publish three tenders for streets and sanitation, and on Thursday 22 the deadlines expire to resurface roads in Alhaurín de la Torre and repair paving in Cártama. Another seven works in Alhaurín de la Torre, Coín and Cártama now have their firm, from the Isaac Peral car park to the Cártama Pueblo pitch, while Alhaurín el Grande weighs offers on two projects. Eleven companies are founded in Coín, Alhaurín el Grande, Alhaurín de la Torre, Pizarra and Cártama. Monda, Álora, Alozaina and Tolox log neither works nor new firms this week.

Every figure links to its official document. If something does not add up, reply and we will correct it within 24 hours. Valle del Guadalhorce Análisis y Negocios Semanal is published by CASAS.ES.

📰 Journalist or publisher? You can republish this analysis and its charts for free under CC BY 4.0, as long as you credit CASAS.ES and link to this page.

Source: CASAS.ES, Valle del Guadalhorce Análisis y Negocios Semanal, 19 October 2026. https://casas.es/en/analysis/valle-del-guadalhorce/2026-10-19/casarabonela-settles-firm-covered-municipal-sports-centre/

RSS