Ceuta comarca · No. 7 · Monday 9 November 2026 · 5-minute read
Ceuta city government tenders 1.98 million in high voltage, November's second-largest works in 21 comarcas
CASAS.ES Newsroom · AI · Official sources
(Madrid time)
Of all the open works published since the 1st in the 21 comarcas covered today, only a 3.59 million flood defence in the Valencia comarca costs more than the port's high-voltage lines. In the Ceuta comarca, the military authorities treat four works at their own sites as resolved, and three new firms have been incorporated.
Bids for the 1.98 million port high-voltage works run until December

- Envelopes must be in by Tuesday 1 December. On Thursday 5 the Ciudad Autónoma de Ceuta published the adaptation of the existing high-voltage lines and networks in the port area where the Servilimpce and Amgevicesa bases are to go. It is tendered at 1,976,719.99 euros excluding VAT, that is, before VAT. It is a public tender, in which companies submit bids until 1 December. Of the open works published since the 1st across the 21 comarcas, only a 3.59 million flood defence in the Valencia comarca is larger.
- The 118 homes at Huerta Molino remain open. The design-and-build tender for the 118 affordable rental homes on plot R3 at Huerta Molino is still accepting bids until 3 December, tendered at 19,965,355.09 euros excluding VAT.
Ceuta's military resolve four repairs worth 88,181.82 euros this week

- A roof, a wall and a leisure zone are now resolved. The Economic Affairs Section of the Comandancia General de Ceuta resolved the waterproofing of the roof of the Cornetín nursery school, belonging to the Ministry of Defence, tendered at 16,363.64 euros excluding VAT, the block wall at the Recarga barracks, for 13,636.36 euros, which already has a company, and the leisure area at the Recarga barracks, for 40,000 euros, going to SEPTA ENERGY. With the Galindo metalwork, the four total 88,181.82 euros tendered and are resolved: the tender is over and the contract has been closed.
- The Galindo metalwork still has no known company. The replacement of the metal window and door frames in building 7, tendered at 18,181.82 euros excluding VAT, shows as resolved, although which company will do it has not yet been published.
- Since June the Comandancia has put out 29 works. The 29 Comandancia works published since June total 645,100.95 euros tendered. ARTECO CEUTA CONSTRUCCIONES takes eight, such as the Casino Militar lift, and SEPTA ENERGY six, such as the fencing of the Polvorín Renegado.
Quays and galleries add up to 6.06 million across seven contracts

- The Estación Marítima carries 35 of every 100 port euros. The energy upgrade of the Estación Marítima, galleries 1 to 6 is resolved for LAMBDA 360 GRADOS EMPRESA CONSTRUCTORA, a limited company in the construction sector, tendered at 2,135,490.89 euros excluding VAT, out of the 6,062,115.16 euros of the seven contracts of the Autoridad Portuaria de Ceuta, the public body that runs the Port of Ceuta. Next come the ferry berths at the Muelle Cañonero Dato, for 1,522,026.88 euros, resolved for Atlantico 18.
- Solar power for the terminal awaits its installer. The solar photovoltaic installation for the terminal and the galleries, tendered at 648,100.42 euros excluding VAT, does not yet have a company. For the reinforcement of the Muelle de Poniente accesses, tendered at 293,951.97 euros excluding VAT, the deadline closed on 28 October, and the Poniente breakwater ramp, up which vehicles drive onto the ship, is resolved but has no company published yet.
- The Poblado Marinero will get two new lifts. The two lifts at the Poblado Marinero, tendered at 200,996.01 euros excluding VAT, are already resolved.
FESA QUALITY lands Virgen de África phase II, Recinto clinic job still unassigned

- FESA QUALITY will renew streets at Virgen de África. FESA QUALITY will carry out the refurbishment of the streets and services of the Virgen de África estate, phase II, tendered at 379,548.03 euros excluding VAT. AFRICANA DE CONTRATAS Y CONSTRUCCIONES has the pavements from the Arab baths to the Muelle Alfau, for 1,575,527.34 euros.
- No company yet has the Recinto works. Ingesa, the state institute that runs public healthcare in Ceuta and Melilla, still has no company for the enclosure and repair of consulting rooms at the Recinto health centre, tendered at 19,545.46 euros excluding VAT. The demolition of the annex of the Consejería de Sanidad, worth 331,385.47 euros, goes to EXCAVACIONES NORTE DE AFRICA, and TOWERS CONSTRUCCIONES Y REFORMAS will build the ramp and doors of the school on Calle Pérez Serrano, for 131,719.05 euros.
- Two builders together will raise 102 rental homes. A joint venture of AFRICANA DE CONTRATAS Y CONSTRUCCIONES and a second builder will build the 102 rental homes at Pozo Rayo, tendered at 19,973,336.13 euros excluding VAT.
Accounting, sport and motoring firms launch, each with 3,000 euros

- Three Ceuta start-ups each put up 3,000 euros. One is L&R CONTABILIDAD, an accounting practice, and the other two deal in sporting goods and in vehicle sales and repairs. Each starts with 3,000 euros of share capital, the money the partners put in when founding the company, 9,000 euros between the three.
- The Consejería de Sanidad opens grants against the digital divide. The call to reduce the digital divide in the Ciudad Autónoma de Ceuta, the notice that opens the window to apply for a grant from the administration that governs the city, is open to applications: who, how much and until when appear only in the official listing. Separately, the Consejería granted a subsidy to the Enfermos sin Fronteras association, money that already has a recipient.
See the CasasValue of buildings in Ceuta on the CASAS.ES map
Up to Sunday 8, in the Ceuta comarca, which is a single city, the Autonomous City tendered the high-voltage lines in the port area, the 118 homes at Huerta Molino stayed open, the Comandancia General marked the tenders for four works at its facilities as resolved while three fresh companies joined the register.
Every figure links to its official document. If something does not add up, reply and we will correct it within 24 hours. Ceuta Análisis y Negocios Semanal is published by CASAS.ES.